Detailed Design, Procurement, and Construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...