Detailed Design, Procurement, and Construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.