FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Technical due diligence on behalf of a financier for an existing soil washing asset in operation, as well as a forward-looking evaluation of the company's pipeline of development opportunities.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
Civil engineering, permit coordination, and construction administration for the re-development of a 0.73-acre existing commercial site for the construction of a Starbucks coffee house.
Civil engineering design and permit coordination services for relocation of an existing sanitary sewer main to accommodate construction of a proposed retaining wall.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
FEL1 and FEL2 Engineering and Owner’s Engineering Services for a 170 TPD Tissue Machine Dry End Replacement project including the Yankee Dryer, Hood, and Air System, as part of a Fleet-wide Rebuild Program.
Preliminary and detailed design engineering to evaluate an existing equipment structure experiencing excessive dynamic loading and responses, determine the root cause, and develop a remediation plan.