This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
FEL1 study for a 6 ktpa battery-grade phosphoric acid plant co-located with 10 ktpa sulfuric acid facility, including process validation and several alternatives analyses.
Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment