Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Civil engineering, permit coordination, and construction administration for the development of 365-acres of existing agricultural land for a 50 MW-DC solar facility.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
FEL1 study for a 6 ktpa battery-grade phosphoric acid plant co-located with 10 ktpa sulfuric acid facility, including process validation and several alternatives analyses.
FEL1 preliminary engineering design for a first-of-a-kind 1KTPA facility to produce Cathode Active Materials for EV batteries, including scale-up from an existing lab-scale processes.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.
Technical due diligence of an existing biomanufacturing company facility including review of process, facility, operations, and overall project execution.