Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.
Independent reviews of several projects ranging from $50-800MM TIC to serve as input prior to final project funding, including visits to project sites to conduct multiday in-person interviews and site walks to supplement desktop review.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
This effort included the front-end engineering, detailed design, and procurement support for a $500 million greenfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary...