Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.
Detailed design engineering for a 10-foot diameter downcomer duct replacement project in an existing 250-foot tall preheater tower, including significant structural reinforcements.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
Detailed design for rerouting broke from an existing linerboard machine to the OCC system to improve water balance, remove fines, and increase fiber recovery.
Civil engineering, permit coordination, and construction administration to support the re-development of a 2.3-acre overflow parking lot at an existing car dealership, including the construction of a new dedicated service shop (8,800-sf).
This $150 million scope consisted of conceptual engineering, front-end engineering, and detailed design to meet an issued environmental consent decree at three similar yet unique metallurgical coking facilities...
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
FEL-2 and full-service detailed design engineering of the ISBL scope for a Dry Bagging expansion at an existing drywall compound manufacturing facility.