This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Detailed design for a maintenance and reliability project on an existing linerboard machine that included the installation of a new dust collection system to address issues with glue and sensor reliability caused by the presence of excess dust.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Detailed design, procurement, and construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
Detailed Design and Construction Oversight of all heavy critical lifts required to construct one of the world’s largest simple cycle gas turbines and its associated components.
Detailed design engineering for replacement of an existing 240V MCC with a new 480V MCC at a specialty chemical facility, including relocation and refeed of wall-mounted loads to the new MCC.
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.