FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.