The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.
Development of a strategic capital expenditure (CAPEX) spending plan to guide the allocation of approximately $50MM for an Owner with a mill in excess of 60 years of age.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.