FEL-2 and full-service detailed design engineering of the ISBL scope for a Dry Bagging expansion at an existing drywall compound manufacturing facility.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Detailed Design Engineering for a new electrolysis hydrogen generation system to inject hydrogen and oxygen into existing kiln burner fuel and combustion air lines, respectively.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
FEED and Detailed Design Engineering for a new tank farm with 300,000 gallons of total capacity to store a combination of Class I, II, and III flammable and combustible liquids.