Conceptual and detailed design engineering, permitting, and construction support for a $15 million 10 MW-DC solar facility located on 50-acres in California.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.