Development of a strategic capital expenditure (CAPEX) spending plan to guide the allocation of approximately $50MM for an Owner with a mill in excess of 60 years of age.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
Preliminary engineering support of a first-of-its-kind ag-based pulping and thermoforming facility, including heat & material balance development and other key activities.
FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
Detailed design, procurement, and construction (EPC) services for a $300 million coal-fired power plant regulatory program including fly ash, bottom ash, and water management conversions.
Front-end engineering services for a pelletized bagasse feedstock facility supporting sustainable aviation fuel production at a co-located sugar mill, including bagasse handling, drying, pelletizing, utility upgrades, and carbon capture.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.