This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.
Civil engineering design, permit coordination, and construction administration for a commercial office park development, master planned to be anchored by a medical office with five (5) accessory building pads for a total 40,000-sf.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
Red Flags Analysis report in support of client’s potential investment in a polystyrene recycling company and the planned scale up of their demonstration-level facility to a commercial scale.
Owner’s Engineering and support during the pre-FID engineering phase (FEL3) for a new 20 million gallons per year Renewable Fuel Oil Production Facility.
Isomer provided full-service FEL3 Engineering for a new ferric chloride production process at an existing specialty chemicals facility, including heat and material and layout development.
Detailed design engineering and construction oversight for a new oil tank farm, oil conditioning system, utilities, and impregnation system for film capacitors.