Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Conceptual engineering evaluating alternatives for a new finished product tank farm, replacing one large field-erected tank with shop-fabricated tanks and assessing enclosure options to minimize operational disruption.
This effort included the front-end engineering, detailed design, and procurement support for a $500 million greenfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary...
Preliminary cost modeling in support of a developer with novel turbine technology intended to be retrofitted or incorporated into chillers for data centers to increase performance.
Civil engineering, permit coordination, and construction administration for the development of a 32.6-acre existing undeveloped site for the construction of a light industrial park
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
FEL3 front-end engineering design for a proprietary bioprocessing facility to utilize specially engineered microorganisms to synthesize bio-based chemicals and produce sustainable commodity products using renewable raw materials, like sugar.
Detailed design engineering to support the installation of a new four million gallon molasses storage tank at an operating sugar mill to improve the business's commercial flexibility.