Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Detailed Design and Construction Oversight of all heavy critical lifts required to construct one of the world’s largest simple cycle gas turbines and its associated components.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design engineering to support the installation of a new rotary strainer for a milling tandem at an operating sugar mill, including a new steel structure and foundation constructed in a heavy brownfield environment.
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
Conceptual engineering for a 960MW-DC,800MW-AC Photovoltaic Solar Farm, for which Isomer provided preliminary single lines, site layout and an annual production report.
FEL2 engineering and cost estimating for a containerboard machine rebuild project including forming, press, dryer, and vacuum system upgrades to improve sheet quality, efficiency, and production.
Detailed design for a maintenance and reliability project on an existing linerboard machine, improving forming section shower system performance and addressing historical water quality issues.