This effort included the detailed design, procurement, and construction management for a $150 million plant to produce Omega-3 fatty acids from micro algae for the animal nutrition industry.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
Civil engineering, permit coordination, and construction administration for the development of a 32.6-acre existing undeveloped site for the construction of a light industrial park
This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.