Technical due diligence for a financier on a Waste Heat to Power asset in construction to support financial close, as well as an evaluation of the company's development pipeline.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Full-service Detailed Design Engineering supporting Balance of Plant design, equipment procurement, and integration of a vendor-supplied anaerobic/aerobic 4.0 MGD Wastewater Treatment System and infrastructure into an existing Linerboard Mill.
Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
Conceptual and detailed design engineering, permitting, and construction support for a $15 million 10 MW-DC solar facility located on 50-acres in California.
Detailed design engineering to support the installation of a new rotary strainer for a milling tandem at an operating sugar mill, including a new steel structure and foundation constructed in a heavy brownfield environment.
Civil engineering, permit coordination, and construction administration for the removal and replacement of an deteriorated parking lot with a 107,500-sf light industrial building.
Technical Confirmatory Due Diligence on behalf of a financier for an existing RNG asset portfolio including the evaluation of pipeline projects to opine on the readiness for financial investment.