Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Civil engineering, permit coordination, and construction administration for the development of 365-acres of existing agricultural land for a 50 MW-DC solar facility.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Heat and Material Balance (HMB) study and preliminary vendor engagement for a 9 MW biomass-to-power generation facility utilizing gasification to produce syngas and biochar, coupled with an ORC system for power generation.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
Civil engineering design, permit coordination, and construction administration for the development of a 2.0-acre site for a 4,500-sf auto glass repair shop and 10,000-sf flex building.