FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.