Front end engineering study to evaluate a deficient vacuum system at an existing ag-based thermoforming facility, including quantifying baseline operation conditions and evaluating potential system improvement modifications.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
Heat and Material Balance (HMB) study and preliminary vendor engagement for a 9 MW biomass-to-power generation facility utilizing gasification to produce syngas and biochar, coupled with an ORC system for power generation.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Civil engineering design and development to support for the conceptual (30%) design of a 75 MW-DC solar facility located on 330-acres in Nevada located within heavy floodplains.