Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
Detailed design, procurement, and construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
This effort included the front-end engineering, detailed design, and procurement support for a $500 million greenfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary...
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.