Front-end engineering and project development services to determine feasibility and order of magnitude costs for a greenfield facility with 150MW Electrolyzers and balance of plant infrastructure.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
Isomer provided detailed design engineering, permitting, and construction support for a $60 million 50 MW-DC solar facility located on 365-acres in Idaho.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Front-end engineering and project development services to determine feasibility and conceptual layout for 314 MW-DC solar facility located on 2,040-acres in Utah.
This effort included the detailed design, permitting, and construction support for the balance of plant (BOP) systems on a 1400 BPD facility converting woody biomass into renewable fuels.