Detailed Design, Procurement, and Construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Technical due diligence on a CO2 capture asset currently under construction, and a broader evaluation of the company's portfolio of development assets for a financing partner.
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
Front-end engineering services for a pelletized bagasse feedstock facility supporting sustainable aviation fuel production at a co-located sugar mill, including bagasse handling, drying, pelletizing, utility upgrades, and carbon capture.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
Process scaleup and project execution support for a first-of-a-kind commercial scale edible fats and oil facility, including a Technology and Scale Up Risk Assessment and Project Execution Road Map.