This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Detailed design engineering for a $45MM TIC laser guided vehicle operated distribution center at an existing sugar mill and refinery, including the integration into an existing warehouse and packaging building.
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
FEL2 and Detailed Design Engineering of ISBL scope for a new Drywall Compound Manufacturing Facility to expand client’s market footprint into a new location and optimize plant performance.
This effort included the detailed design, procurement, and construction management for a $150 million plant to produce Omega-3 fatty acids from micro algae for the animal nutrition industry.