Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $3MM TIC project to expand an existing vacuum system at a 25 TPD ag-based pulp thermoforming facility.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.
The scope consisted of developing a companywide reliability program for a major pulp and paper corporation. The project team led a group that included contractors from three separate companies with extensive reliability programs...
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
This project included front-end engineering and project development support for a brownfield non-wood ag-based pulping and molding facility. The facility was designed to provide a finished product capacity of 15,000 bone-dry metric tons per year...
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.