This project included front-end engineering and project development support for a brownfield non-wood ag-based pulping and molding facility. The facility was designed to provide a finished product capacity of 15,000 bone-dry metric tons per year...
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.
Front-end engineering study for a new low consistency storage tower and pump integrated into an existing 30 TPD ag-based fiber pulping process facility.