FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.