This effort included the detailed design, procurement, and construction management for a $80 million brownfield polymer manufacturing facility expansion.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This effort included the detailed design, procurement, and construction management for a $150 million plant to produce Omega-3 fatty acids from micro algae for the animal nutrition industry.
Detailed design, procurement, and construction for a $100 million fly ash, bottom ash, and pyrites handling and transport conversion EPC project to meet Coal Combustion Residuals (CCR) environmental regulations.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
This project effort included detailed design and construction support for a turnkey, full-scale Ethylene Oxide production facility along the Delaware River.
This effort included the detailed design, permitting, and on-site construction support for a $75 million greenfield plant to produce food-grade vegetable oil.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.