Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Front-end engineering and project development services to determine feasibility and conceptual layout for 314 MW-DC solar facility located on 2,040-acres in Utah.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
Civil engineering design and development to support for the conceptual (30%) design of a 75 MW-DC solar facility located on 330-acres in Nevada located within heavy floodplains.
Front end engineering design and technology trials support for a liquor coproduct contaminant reduction system at an existing 30TPD ag-based pulp mill.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
The scope of this effort consisted of front-end engineering for a significant capacity increase for an existing polymer facility. The facility produces high-performance elastomers used as replacements for rubber. The project team...
Front-end engineering and project development services to assist developer in determining the feasibility and estimated construction cost of various projects throughout the upstate of South Carolina.
The scope consisted of detailed engineering and procurement support for a brownfield energy project at an existing paper mill. The project included a circulating fluidized bed (CFB) boiler and double auto-extraction steam turbine generator...