FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
Front-end engineering and project development services to assist developer in determining the feasibility and estimated construction cost of various projects throughout the upstate of South Carolina.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
This scope consisted of multiple layers of support for the re-development of a 48 MW biomass-fired power plant that had been moth-balled in the middle of the initial construction process. As the project found new life...