This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.
Technical advisory services in support of novel co-located phosphoric and sulfuric acid production facilities, including risk analysis and development of an order-of-magnitude capital cost estimating tool.
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
FEL-2 design to support upgrades to an existing linerboard paper machine roll handling line, including conveyors, a lowerator, and shipping floor conveyors for loading finished product rolls into railcars.