Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
FEL3 Engineering package supporting the Balance of Plant design and integration of a vendor-supplied 4.0 MGD Wastewater Treatment System into an existing linerboard mill.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
Conceptual and detailed design engineering, permitting, and construction support for a $15 million 10 MW-DC solar facility located on 50-acres in California.