Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Front-end engineering and project development services to determine feasibility and conceptual layout for 400 MW-DC solar facility with 200-MW BESS located in Nebraska.
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
FEL1 preliminary engineering design for a first-of-a-kind 1KTPA facility to produce Cathode Active Materials for EV batteries, including scale-up from an existing lab-scale processes.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
Civil engineering design, permit coordination, and construction administration for a commercial office park development, master planned to be anchored by a medical office with five (5) accessory building pads for a total 40,000-sf.
The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
Front-end engineering and project development services to determine feasibility and conceptual layout for 210 MW-DC solar facility located in Arizona.