Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Civil engineering design, permit coordination, and construction administration for the development of a 2.0-acre site for a 4,500-sf auto glass repair shop and 10,000-sf flex building.
Conceptual civil engineering and site plan development to support the preliminary plan approval for a 12,000-square foot indoor pickleball and badminton facility.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
Development of a strategic capital expenditure (CAPEX) spending plan to guide the allocation of approximately $50MM for an Owner with a mill in excess of 60 years of age.
FEL1 engineering design for a novel critical elements recovery facility funded by ARPA-e to process 1 ktpd of ultramafic tailings, integrating direct air capture of CO2 for carbon sequestration and electrolytic production of sulfuric acid.
FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...