FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
Multi-discipline front-end engineering and estimating services for a facility using a proprietary process to convert waste cellulose into consumer product replacements.
Detailed design engineering to support the installation of a new rotary strainer for a milling tandem at an operating sugar mill, including a new steel structure and foundation constructed in a heavy brownfield environment.
FEL2 front-end engineering design to evaluate a deficient vacuum seal water cooling loop at an existing molded fiber facility and replace an undersized cooling tower and supply pumps.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
Preliminary engineering for a nutrient recovery facility co-located at an existing RNG production facility, converting ammonia nitrogen into a marketable organic fertilizer product using a proprietary process.
Civil engineering, permit coordination, and construction administration to support the re-development of a 2.3-acre overflow parking lot at an existing car dealership, including the construction of a new dedicated service shop (8,800-sf).