Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Full-service Detailed Design Engineering supporting Balance of Plant design, equipment procurement, and integration of a vendor-supplied anaerobic/aerobic 4.0 MGD Wastewater Treatment System and infrastructure into an existing Linerboard Mill.
Detailed design for rerouting broke from an existing linerboard machine to the OCC system to improve water balance, remove fines, and increase fiber recovery.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.
New kraft liner machine and building, OCC facility, highly modified fiberline, boiler natural gas conversion, and electrical infrastructure additions to accommodate virgin and recycled fiber linerboard production.
Detailed design and structural dynamics engineering evaluation to analyze an existing paper machine dryer section for an unbalance issue at an existing facility.
Civil engineering, permit coordination, and construction administration to support the re-development of a 2.3-acre overflow parking lot at an existing car dealership, including the construction of a new dedicated service shop (8,800-sf).
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
The scope consisted of developing a companywide reliability program for a major pulp and paper corporation. The project team led a group that included contractors from three separate companies with extensive reliability programs...
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.