Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.
FEL2 through detail design engineering for a velvet manufacturer facility relocation. Scope of work included a site walk down, equipment and facility studies, 3D modeling (including VR walkthrough), heavy civil coordination, and wetlands study.
Front-end engineering for the addition of a 3,000 TPY rolled ornamental stainless steel, high-frequency production line at an existing rolled tubes production facility.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Technical due diligence of an existing biomanufacturing company facility including review of process, facility, operations, and overall project execution.
The scope consisted of detailed engineering and procurement support for a brownfield energy project at an existing paper mill. The project included a circulating fluidized bed (CFB) boiler and double auto-extraction steam turbine generator...
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.