FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
Civil engineering, permit coordination, and construction administration for the removal and replacement of an deteriorated parking lot with a 107,500-sf light industrial building.
Project management and construction oversight for an $8 million chemical manufacturing facility upgrade, including direct supervision of detailed design and construction bid process.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
Detailed design, procurement, and construction support for a $300 million brownfield, 100% recycled (OCC) linerboard machine installation to produce premium and back ply liner.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
Front-end engineering for the addition of a 3,000 TPY rolled ornamental stainless steel, high-frequency production line at an existing rolled tubes production facility.
Development of a strategic capital expenditure (CAPEX) spending plan to guide the allocation of approximately $50MM for an Owner with a mill in excess of 60 years of age.
Detailed design and FEL2 for a 25 TPD molded fiber production facility. Design included new repulping, stock prep, thermoforming, and utility systems located in an existing manufacturing facility.
This project focused on installation a new 1 million gallon molten sulfur tank in an existing sulfuric acid production facility. The design including supporting piping electrical and structural modifications.