Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
FEL2 preliminary study and detailed design engineering for a new concrete containment area for chemical railcar loading at an existing production facility.
Capital cost estimating and detailed design engineering for a $5MM TIC project to upgrade dry end handling capabilities at an existing chemicals facility.
Conceptual engineering to support the evaluation of an existing anaerobic digestion facility to receive additional liquid waste feedstocks for co-digestion.
This effort included detailed design mechanical, piping, electrical and structural services to support a $500 million expansion to add two new sustainable technology product lines at an existing automotive manufacturing facility.
FEL3 engineering package for the installation of two new reactors to replace an existing end-of-life reactor vessel at a specialty chemicals facility.
Civil engineering design and permit coordination services for relocation of an existing sanitary sewer main to accommodate construction of a proposed retaining wall.
This effort included the detailed design and construction support to install a River Water Intake System and Raw Water Treatment system to support an Ammonium Nitrate Solution (ANSol) plant in Tennessee.