This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
FEED Package included developing a TIC estimate to replace existing utility boilers at a batch process plant, including evaluating boiler technology, layout and NFPA code for an existing building.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
This effort included permitting, sampling and on-site chemical inventory to support the closure of a manufacturing facility as well as the on-site wastewater treatment plant.
Comprehensive structural inspection and due diligence reporting for fleet of 15+ production and distribution facilities, working to identify immediate risks to market supply.
This scope consisted of a detailed technical review conducted supporting due diligence for a project where landfill gas (LFG) was extracted via an existing system. The extracted LFG was then to-be-processed and converted...
Detailed design, procurement, and construction (EPC) services for a $130 million greenfield bio-energy center to generate cellulosic ethanol from yard and wood waste.
This effort included developing a comprehensive independent engineering report to assess a biosolids-only downdraft gasification system. The gasification system is located in a repurposed building adjacent to a local sewage authority...
This effort included the detailed design, permitting, and construction support for a $400 million, 850,000 sq. foot state of the art particleboard manufacturing plant.