Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
FEL1 and detailed design to double the capacity of an existing ag-pulp feedstock processing line, including modifications to material handling, hammer mill, pneumatic transport, and conveying systems.
Detailed design and engineering services for a $45 million containerboard machine rebuild project at an existing facility featuring a new shoe press and an iTable to replace the existing top-wire former.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
This effort included the front-end engineering, detailed design, and construction oversight over the complete winder replacement of the paper machine.
Fluff Pulp Machine Upgrade Project with the objective to increase production of the paper machine through machine and other auxiliary system modifications.
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.