Detailed design for a maintenance and reliability project on an existing linerboard machine that included the installation of a new dust collection system to address issues with glue and sensor reliability caused by the presence of excess dust.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
This effort included the FEED, detailed design, permitting, and construction support for a 6500 BPD Renewable Diesel Plant, utilizing Haldor Topsoe technology.
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
This effort included the front-end engineering, detailed design, and procurement support for a $500 million greenfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary...
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...
Detailed design and project management for a $100 million, 2,000 MTPD Semi-Dry Cement Plant upgrade, featuring a new pyroline, at an existing facility in Oklahoma.
This project included detailed design and procurement support for the main polysilicon production building, the largest project on the campus of a multi-billion-dollar greenfield manufacturing site...