This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...
Front-end engineering for the addition of a 3,000 TPY rolled ornamental stainless steel, high-frequency production line at an existing rolled tubes production facility.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
Front-end engineering and project development support for a 450,000 TPA greenfield wood pellet plant. Roundwood and residuals were used for feedstock. Facility included rotary drying, rail and truck loadout capability.
This effort included the detailed design and procurement support for a $250 million brownfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary to produce premium quality parent rolls..
FEED and Detailed Design Engineering for a new tank farm with 300,000 gallons of total capacity to store a combination of Class I, II, and III flammable and combustible liquids.
Structural feasibility study to evaluate the potential addition of rooftop solar panels to multiple existing structures at a chemicals manufacturing facility, as well as the potential for adding panels over existing stormwater infrastructure.
Front-end engineering and project development services to assist developer in determining the feasibility and estimated construction cost of various projects throughout the upstate of South Carolina.
This $150 million scope consisted of conceptual engineering, front-end engineering, and detailed design to meet an issued environmental consent decree at three similar yet unique metallurgical coking facilities...
This project included a contract for detailed design following a transition from another engineering firm at less than 10% complete; however, construction activities had already begun in the field. The scope of the project...