This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
Existing mill conversion from fine paper to linerboard production using 100% OCC furnish including new OCC facility and warehouse, conversion of existing machine, conversion of two boilers, and other utility upgrades.
This effort included the completion of the conceptual design (FEL2) phase for a $5 million USD water sustainability program for an existing Fiber Optics facility with a goal to reduce water consumption at the site by 80%.
Preliminary engineering in support of a developer commercializing a first-of-a-kind process to capture and store CO2 via natural water sources adjacent to industrial point source emitters.
Civil engineering, permit coordination, and construction administration for the development of a 32.6-acre existing undeveloped site for the construction of a light industrial park
FEL1 and capital cost estimate development for the addition of a hydrocyclone cleaner to protect refiners from contaminants at an existing 30TPD ag-based pulping line.
Comprehensive site logistics study to evaluate and improve inbound and outbound truck routing for a cement manufacturing facility to relieve heavy onsite traffic congestion.
Capital cost estimating for a portfolio of small plant projects up to $7 million, including FEL engineering and an AACE Class 3 estimate and accompanying report.
FEL3 front-end engineering design for a proprietary bioprocessing facility to utilize specially engineered microorganisms to synthesize bio-based chemicals and produce sustainable commodity products using renewable raw materials, like sugar.
Detailed design engineering to support the installation of a new four million gallon molasses storage tank at an operating sugar mill to improve the business's commercial flexibility.