Technical advisory services in support of novel co-located phosphoric and sulfuric acid production facilities, including risk analysis and development of an order-of-magnitude capital cost estimating tool.
Detailed design engineering in a design-build arrangement for a 60,000 SF roll finishing and shipping warehouse install at an existing pulp & paper mill as part of a major modernization effort.
Detailed design for a maintenance and reliability project on an existing linerboard machine, including improvements for the existing tail cutter system to reduce damage to felts and improve overall machine runnability.
Detailed design and structural dynamics engineering evaluation to analyze a 4000-hp existing power plant ID fan for an unbalance issue at an existing facility.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
Front end engineering study to evaluate the feasibility of firing a secondary biomass fuel in three separate biomass boilers at an existing facility in an effort to reduce the consumption of the primary fuel source.
Detailed design engineering services in support of a first-of-its-kind plant-based protein production facility, including sitewide civil engineering and utility distribution.
Pre-FEL study and FEL1 design of a primarily greenfield 150TPD ag-based pulp molded fiber facility, including feedstock handling and separation, material storage, semi-chem pulping, stock preparation, and molding.
This effort included detailed engineering on a four project Anaerobic Digestion to biogas program with site locations in Georgia and California. The facilities were located on existing dairy farms of approximately 12,000 cows each...
Isomer provided Technical Due Diligence for a potential investment in a solar development platform, reviewing solar and BESS production targets, technology, EPC execution capabilities, and project economics to identify critical risks and red flags.