The effort included the detailed design and construction oversight over the winder rebuild of the paper machine, which included new safety systems, slitter, feeding and gluing capabilities.
This effort included the review of process drawings, on-site facilitation of dust hazard analysis using a what-if method, as well as review of applicable NFPA standards for a wood-products facility.
This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...
Isomer provided detailed design engineering, permitting, and construction support for a renewable natural gas facility located at the Anson County Landfill.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
Front-end engineering services and project development support for a new three stage feedstock cleaning/storage system at an existing non-wood ag-based pulping and molding facility.
Detailed design, procurement, and construction for a $100 million fly ash, bottom ash, and pyrites handling and transport conversion EPC project to meet Coal Combustion Residuals (CCR) environmental regulations.
Detailed Design for a $20 million white liquor optimization project consisting of a new three-story pressure disc filter process building, causticizer, clarifier and lime mud filter upgrades.
Conceptual engineering for a 960MW-DC,800MW-AC Photovoltaic Solar Farm, for which Isomer provided preliminary single lines, site layout and an annual production report.