The scope consisted of developing a companywide reliability program for a major pulp and paper corporation. The project team led a group that included contractors from three separate companies with extensive reliability programs...
This effort included the detailed design, material procurement, construction planning and construction management for a $3 million brownstock washing system upgrade.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.
This scope consisted of front-end engineering and detailed design to increase the bark firing capacity of an existing combination boiler at a paper mill. Initial studies identified issues, and the project team proceeded...
Project Management and Construction Oversight services for a 15TPD ag-based fiber thermoforming line retrofit, including demolition of old equipment and design/installation of new equipment.
This scope consisted of full-cycle project support from front-end engineering through startup for the conversion of an existing power boiler from coal firing to natural gas at an existing paper mill. The project installed six new...
FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
The scope consisted of detailed engineering and procurement support for a brownfield energy project at an existing paper mill. The project included a circulating fluidized bed (CFB) boiler and double auto-extraction steam turbine generator...
FEL2 Engineering and Owner’s Engineering Services for a 280 TPD Tissue Machine Process Air System Replacement project as part of a Fleet-wide Rebuild Program.