FEL2 engineering and cost estimating for a containerboard machine rebuild project including forming, press, dryer, and vacuum system upgrades to improve sheet quality, efficiency, and production.
This effort included detailed design mechanical, piping, electrical and structural services to support a $500 million expansion to add two new sustainable technology product lines at an existing automotive manufacturing facility.
Civil engineering, permit coordination, and construction administration for the development of a 32.6-acre existing undeveloped site for the construction of a light industrial park
The scope consisted of detailed engineering and procurement support for a brownfield energy project at an existing paper mill. The project included a circulating fluidized bed (CFB) boiler and double auto-extraction steam turbine generator...
Civil engineering, permit coordination, and construction administration for the removal and replacement of an deteriorated parking lot with a 107,500-sf light industrial building.
Preliminary engineering services in support of a thermoforming capacity increase at an existing molded fiber production facility, including a cost-benefit analysis and extensive utility study.
FEL2 front-end engineering design for a first-of-a-kind 1000TPA facility to recover monomers from spent textiles via a proprietary chemical recycling process, including scale-up from an existing lab-scale processes.
This effort included the FEED package, detailed design, and construction support for restarting an existing Paper Machine and supporting systems and infrastructure at a legacy mill.
The effort included the front-end engineering and detailed design services for installing a 15 TPD Green Hydrogen Production and Liquefaction Plant on a greenfield site.
Front end engineering study to evaluate a deficient vacuum system at an existing ag-based thermoforming facility, including quantifying baseline operation conditions and evaluating potential system improvement modifications.