Basic engineering phase (FEL-3) for a $5 million project to add silicone-based and water-based defoamers process lines in an existing chemical processing facility.
Front-end engineering and project development services to assist developer in determining the feasibility and estimated construction cost of various projects throughout the upstate of South Carolina.
Detailed design including site development, foundations, electrical, and mechanical design for a 40,000SF maintenance warehouse built to service steel processing equipment
FEL3 front-end engineering design for a proprietary bioprocessing facility to utilize specially engineered microorganisms to synthesize bio-based chemicals and produce sustainable commodity products using renewable raw materials, like sugar.
Fluff Pulp Machine Upgrade Project with the objective to increase production of the paper machine through machine and other auxiliary system modifications.
This effort included the front-end engineering, detailed design, and construction oversight to convert all machine DC motors and drives to AC power. The PIVs were also replaced with AC motors.
Performed third-party engineering due diligence to identify major risks and red flags for a project installing a Textile Recycling Facility into an existing mothballed manufacturing facility.
Red Flags Analysis report in support of client’s potential investment in a polystyrene recycling company and the planned scale up of their demonstration-level facility to a commercial scale.
Front end engineering, detailed design, and Project Management and Construction Oversight services for a $5MM TIC warehouse expansion project at a 25 TPD ag-based pulp thermoforming facility.