Root cause analysis for a significant vibration issue affecting a group of dryer cans on an existing paper machine, including both onsite and offsite analysis.
This effort centered around providing early-stage project development services for a brownfield wood pellet plant rated at 150,000 metric tons per year. Residuals from nearby sawmills made up all of the feedstock used for this project. ..
Front-end engineering and project development services to determine feasibility and conceptual layout for 314 MW-DC solar facility located on 2,040-acres in Utah.
Front end engineering study to evaluate the feasibility of installing pressure screening systems on existing stock approach loops at an ag-based pulp thermoforming facility.
This effort included the FEL2, FEL3 and detailed design for a new glass furnace structure, raw material feed system, and packaging line for a reflective glass bead production facility.
This $150 million scope consisted of conceptual engineering, front-end engineering, and detailed design to meet an issued environmental consent decree at three similar yet unique metallurgical coking facilities...
This effort included the detailed design and procurement support for a $400 million brownfield through-air-drying (TAD) tissue machine installation and supporting infrastructure. The facility design included all processes necessary...
This effort included the FEL3 and detailed design for a new reactor structure, associated equipment and supporting insfras turecture at an existing surfactant production facility.
FEL2 Engineering and Owner’s Engineering Services for a 180 TPD Tissue Machine Yankee Dryer Hood Replacement project as part of a Fleet-wide Rebuild Program.
This effort included the front-end engineering, detailed design, and procurement support for a $500 million greenfield through-air-drying (TAD) tissue machine installation. The facility design included all processes necessary...